The biggest intercrete project completed in the Southern Hemisphere at the time, this project involved repairing 6km of cracks on the floor and a full coat of 3mm thickness intercrete product. With the tank losing 1.2 megalitres per day of water before the remediation works were undertaken, water loss after the repairs was reduced by three quarters.